Project Summary
Project Summary
Sector Name : ATOMIC ENERGY.
Agency Name : NUCLEAR POWER CORPORATION OF INDIA LIMITED.
Project Name : KUDANKULAM APP (NPCIL).

Reported Date : 07-NOV-17

MOU Status : Project Under MOU for 2016-2017

Monthly Report : 9 / 2017

Cost Overrun (%)-   70.54

Time Overrun (Months)-    105

Total/Pending/Completed Milestone - 102 / 0 / 102

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
13171022462

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2229050022340

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20080/09/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
920

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project is completed in March-2017. Commercial Operation of Kudankulam Nuclear Power Project Unit -2 has been declared with effect from 1100 hours of March 31, 2017. The start of commercial operation of KKNPP-2 has marked the completion of KKNPP-1&2 project. The finalisation of completion cost is in process.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone