Project Summary
Project Summary
Sector Name : ATOMIC ENERGY.
Agency Name : URANIUM CORPORATION OF INDIA LIMITED.
Project Name : NEW URANIUM ORE PROCESSING MILL (UCIL).

Reported Date : 12-JUN-09

Monthly Report : 3 / 2009

  

   

Total/Pending/Completed Milestone - 36 / 0 / 36

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
343.260343.26

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0328.050328.05

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20060/03/2009

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks