Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NORTHERN COAL FIELDS LIMITED.
Project Name : DUDHICHUA (NCL).

Reported Date : 18-JUL-06

Monthly Report : 4 / 2004

  

   

Total/Pending/Completed Milestone - 4 / 0 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
868.9301281.39

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1233.4330.3701263.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/19980/03/2004

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
25-MAY-040Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks