Project Summary
Project Summary
Sector Name : COAL.
Agency Name : SINGARENI COLLIERS COMPANY LIMITTED.
Project Name : MEDAPALI (SCCL).

Reported Date : 18-JUL-06

Monthly Report : 5 / 2001

  

   

Total/Pending/Completed Milestone - 7 / 0 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
219.820219.82

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
39.770039.77

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20010/03/2001

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
11-JUN-010Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Delay in Civil Works5/20010/0PendingNormal
Forest Land5/20010/0PendingNormal