Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NORTHERN COAL FIELDS LIMITED.
Project Name : NIGAHI OC EXPANSION(NCL).

Reported Date : 18-JUL-06

Monthly Report : 4 / 2004

  

   

Total/Pending/Completed Milestone - 13 / 0 / 13

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1846.4901846.49

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1369.451.1901370.64

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20040/03/2004

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
25-MAY-040Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Award of contract4/20040/0PendingNormal