Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : TPS-II EXPANSION (1470MW TO 1970MW) (NLC).

Reported Date : 07-OCT-15

Monthly Report : 8 / 2015

  

   

Total/Pending/Completed Milestone - 23 / 0 / 23

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2030.783583.773583.77

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3185.9527.822.143215.91

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20093/20134/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
74.630

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-MAR-1512-DEC-0798Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks