Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : EXPANSION OF MINE-II (10.5 MTPA TO 15.0 MTPA) (NLC).

Reported Date : 05-MAY-10

Monthly Report : 3 / 2010

  

   

Total/Pending/Completed Milestone - 23 / 0 / 23

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2161.282295.932295.93

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1510.54279.3718.431808.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20090/03/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3200

Ministry Review Date

LatestLastPhysical Progress (%)Status
26-MAY-0912-DEC-07100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks