Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : BARSINGSAR TPS (2 125MW) (NLC).

Reported Date : 25-APR-12

Monthly Report : 2 / 2012

  

   

Total/Pending/Completed Milestone - 26 / 0 / 26

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1114.181626.091868.71

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1576.46138.2601714.72

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20090/01/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
60.560.5

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-AUG-1112-DEC-070Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks