Project Summary
Project Summary
Sector Name : COAL.
Agency Name : NEYVELI LIGNITE CORPORATION.
Project Name : BARSINGSAR MINE 2.10 MTPA LIGNITE (NLC).

Reported Date : 19-NOV-10

Monthly Report : 9 / 2010

  

   

Total/Pending/Completed Milestone - 19 / 0 / 19

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
254.071687.781687.78

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
214.511473.2701687.78

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20090/09/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
184.890

Ministry Review Date

LatestLastPhysical Progress (%)Status
28-APR-1012-DEC-07100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks