Project Summary
Project Summary
Sector Name : COAL.
Agency Name : MAHANADI COAL FIELDS LIMITED.
Project Name : BHUBANESHWARI EXPANSION OCP (MAHANADI COALFIELDS LTD.).

Reported Date : 18-JUL-08

Monthly Report : 1 / 2008

  

   

Total/Pending/Completed Milestone - 4 / 0 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
336.680336.68

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
00033.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20120/03/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks