Project Summary
Project Summary
Sector Name : MINES.
Agency Name : NATIONAL ALUMINUM COMPANY LIMITED (NALCO).
Project Name : EXPN OF BAUXITE MINE AND ALUMINA REFINERY(NALCO).

Reported Date : 18-JUL-06

MOU Status :

Monthly Report : 12 / 2001

Cost Overrun (%)-   0

Time Overrun (Months)-    9

Total/Pending/Completed Milestone - 17 / 0 / 17

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1664.601664.6

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1119.4112.2601231.66

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20010/012/2001

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
161.820

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone