Project Summary
Project Summary
Sector Name : MINES.
Agency Name : NATIONAL ALUMINUM COMPANY LIMITED (NALCO).
Project Name : EXPN. OF CAPACITY OF SMELTER AND CPP (NALCO).

Reported Date : 18-JUL-06

Monthly Report : 9 / 2004

  

   

Total/Pending/Completed Milestone - 24 / 0 / 24

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2061.9802061.98

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1593.05001593.05

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20020/09/2004

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks