Project Summary
Project Summary
Sector Name : MINES.
Agency Name : NATIONAL ALUMINUM COMPANY LIMITED (NALCO).
Project Name : INSTALLATION OF 8TH UNIT OF CAPTIVE POWER PLANT. (NALCO).

Reported Date : 18-JUL-06

Monthly Report : 2 / 2004

  

   

Total/Pending/Completed Milestone - 22 / 0 / 22

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4800480

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
204.1562.830266.98

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20040/02/2004

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks