Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : SINTER PLANT-3 BHILAI SP(SAIL).

Reported Date : 18-JUL-06

MOU Status :

Monthly Report : 3 / 2001

Cost Overrun (%)-   26.81

Time Overrun (Months)-    27

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
636.810807.54

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
595.2148.750743.95

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/19980/03/2001

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
102.56120

Ministry Review Date

LatestLastPhysical Progress (%)Status
02-NOV-000Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone