Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : RASTRIYA ISPAT NIGAM LIMITED.
Project Name : COKE OVEN BATTERY NO. 4(PHASE-1) (RINL).

Reported Date : 23-JUL-09

MOU Status :

Monthly Report : 4 / 2009

Cost Overrun (%)-   23.93

Time Overrun (Months)-    28

Total/Pending/Completed Milestone - 21 / 0 / 21

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
286.630355.21

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
300.860.39301.25

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20060/04/2009

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
27-JAN-060Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Delay in supply of indigenous equipments4/2006/PendingNormal
Delay in Civil Works4/2006/PendingNormal
Delay in Supply of Equipments4/2006/PendingNormal

Ongoing Milestone

Completed Milestone