Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : RASTRIYA ISPAT NIGAM LIMITED.
Project Name : EXPANSION OF LIQUID STEEL CAPACITY FROM 3MT TO 6.3MT (RINL).

Reported Date : 04-DEC-15

MOU Status : Project Under MOU for 2015-2016

Monthly Report : 10 / 2015

Cost Overrun (%)-   41.41

Time Overrun (Months)-    66

Total/Pending/Completed Milestone - 70 / 0 / 70

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
86921229112291

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
11284.83198.29011483.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/200910/20124/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2500

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-SEP-1509-NOV-060Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Award of contract4/2006/PendingNormal

Ongoing Milestone

Completed Milestone