Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : LPG PIPELINE FROM JAMNAGAR TO LONI(GAIL).

Reported Date : 18-JUL-06

MOU Status :

Monthly Report : 6 / 2001

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1229.4501229.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1071.484.1101075.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20010/04/2001

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1850

Ministry Review Date

LatestLastPhysical Progress (%)Status
13-DEC-000Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone