Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : LPG RECOVERY PLANT(GAIL), GANDHAR.

Reported Date : 18-JUL-06

Monthly Report : 3 / 2001

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
361.370361.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
81.15250.040331.19

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20020/04/2001

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
75179.92

Ministry Review Date

LatestLastPhysical Progress (%)Status
13-DEC-000Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks