Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : INTEGRATED PARA-XYLENE(IOCL).

Reported Date : 19-DEC-06

Monthly Report : 8 / 2006

  

   

Total/Pending/Completed Milestone - 129 / 0 / 129

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
422804562

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
31671444353746

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20050/08/2006

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10770

Ministry Review Date

LatestLastPhysical Progress (%)Status
29-NOV-040Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks