Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : C2-C3 AND LPG RECOVERY FROM LNG, DAHEJ (ONGC).

Reported Date : 22-SEP-11

Monthly Report : 7 / 2011

  

   

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
900.921493.49976.08

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
766.677.650774.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20087/20104/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
29.260

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JUL-1130-APR-08100Completed

Monthly Status

Background Information

PLANT IS MECHANICALLY COMPLETED. COMMISSIONING TO BE CARRIED OUT.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks