Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : POL JETTY AT JAWHARLAL NEHRU PORT(BPCL).

Reported Date : 18-JUL-06

Monthly Report : 4 / 2002

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
198.020150

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
80.4560.550141

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20010/02/2002

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
16-JUL-010Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks