Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : CHENNAI PETROLEUM CORPORATION LIMITED.
Project Name : REFINERY EXPANSION CUM.MOD. PROJECT(CPCL).

Reported Date : 18-JUL-06

Monthly Report : 8 / 2004

  

   

Total/Pending/Completed Milestone - 81 / 0 / 81

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2360.3802360.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2060.4184.4502144.86

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20030/08/2004

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1500

Ministry Review Date

LatestLastPhysical Progress (%)Status
09-JUL-030Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks