Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : KONDAPALLY-LANCO PIPELINE(GAIL).

Reported Date : 18-JUL-06

Monthly Report : 2 / 2002

  

   

Total/Pending/Completed Milestone - 10 / 0 / 10

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
299.50200

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
64.4492.240156.68

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20020/08/2001

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
186.810

Ministry Review Date

LatestLastPhysical Progress (%)Status
16-JUL-000Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks