Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : CHENNAI-TRICHY-MADURAI PRODUCT PIPELINE (IOCL).

Reported Date : 18-JUL-06

Monthly Report : 12 / 2005

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
363.210363.21

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
221.6787.990309.66

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20050/012/2005

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
120.080

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks