Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : KOCHI REFINERIES LIMITED.
Project Name : CRUDE OIL RECEIPT FACLITIES (KOCHI REFINERIES LTD).

Reported Date : 18-JUL-08

Monthly Report : 11 / 2007

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
622.820821

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
000540.62

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20070/012/2007

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks