Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : INST. OF FACILITIES FOR IMPROVEMENT IN DIESEL QUALITY (IOCL).

Reported Date : 04-FEB-11

Monthly Report : 11 / 2010

  

   

Total/Pending/Completed Milestone - 36 / 0 / 36

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
187628693155

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2550.3419702747.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20090/02/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2900

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks