Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : TALCHER STPP ST-II(NTPC).

Reported Date : 18-JUL-06

MOU Status :

Monthly Report : 3 / 2005

Cost Overrun (%)-   0

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 92 / 0 / 92

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6648.8306648.83

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4175.12203.2304378.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20060/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
541.82294.11

Ministry Review Date

LatestLastPhysical Progress (%)Status
21-JUL-040Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone