Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL HYDRO-ELECTRIC POWER CORPORATION.
Project Name : DULHASTI HYDROELECTRIC PROJECT(NHPC).

Reported Date : 27-AUG-07

Monthly Report : 3 / 2007

  

   

Total/Pending/Completed Milestone - 9 / 0 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
183.4504982.62

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4679.15281.2604960.41

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/19900/03/2007

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
199358

Ministry Review Date

LatestLastPhysical Progress (%)Status
07-FEB-060Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Delay in Civil Works3/20010/0PendingNormal
Others3/20010/0PendingNormal