Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL HYDRO-ELECTRIC POWER CORPORATION.
Project Name : DHAULIGANGA H.E.P.-I (NHPC).

Reported Date : 18-JUL-06

MOU Status :

Monthly Report : 10 / 2005

Cost Overrun (%)-   162.19

Time Overrun (Months)-    84

Total/Pending/Completed Milestone - 36 / 0 / 36

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
601.9801578.31

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1584.694.4101679.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/19980/010/2005

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
90.60

Ministry Review Date

LatestLastPhysical Progress (%)Status
01-AUG-050Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone