Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NORTH EAST ELECTRIC POWER CORPORATION.
Project Name : RANGANADI HYDRO ELECTRIC PROJECT, STAGE I(NEEPCO).

Reported Date : 18-JUL-06

MOU Status :

Monthly Report : 4 / 2002

Cost Overrun (%)-   365.33

Time Overrun (Months)-    91

Total/Pending/Completed Milestone - 7 / 0 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
312.7801455.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1398.45001398.45

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/19940/03/2002

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
26-NOV-010Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Delay in Civil Works4/20020/0PendingNormal

Ongoing Milestone

Completed Milestone