Project Summary
Project Summary
Sector Name : POWER.
Agency Name : THDC INDIA LIMITED.
Project Name : TEHRI DAM AND H.P.P.(THDCL).

Reported Date : 27-AUG-07

MOU Status :

Monthly Report : 3 / 2007

Cost Overrun (%)-   175.95

Time Overrun (Months)-    96

Total/Pending/Completed Milestone - 17 / 0 / 17

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2963.6608178.22

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
7482.78540.047.728030.54

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/19990/03/2007

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
244.84558.5

Ministry Review Date

LatestLastPhysical Progress (%)Status
21-NOV-0621-NOV-060Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Delay in supply of imported equipments0/00/0PendingNormal
Others3/20010/0PendingNormal
Others3/20010/0PendingNormal

Ongoing Milestone

Completed Milestone