Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : SIMHADRI TPP ST-I (NTPC).

Reported Date : 18-JUL-06

MOU Status :

Monthly Report : 9 / 2002

Cost Overrun (%)-   13.81

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 34 / 0 / 34

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3650.7904155.03

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2671.79175.5802847.37

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20020/012/2002

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
422.230

Ministry Review Date

LatestLastPhysical Progress (%)Status
08-AUG-020Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone