Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL HYDRO-ELECTRIC POWER CORPORATION.
Project Name : TEESTA HE PROJECT STAGE-V (NHPC).

Reported Date : 24-JUL-08

MOU Status :

Monthly Report : 3 / 2008

Cost Overrun (%)-   13.52

Time Overrun (Months)-    13

Total/Pending/Completed Milestone - 41 / 0 / 41

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2198.0402495.29

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2157.44291.0811.372459.89

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20070/03/2008

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2000

Ministry Review Date

LatestLastPhysical Progress (%)Status
17-MAY-070Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Others12/20040/0PendingNormal

Ongoing Milestone

Completed Milestone