Project Summary
Project Summary
Sector Name : POWER.
Agency Name : THDC INDIA LIMITED.
Project Name : KOTESHWAR HEP(THDC).

Reported Date : 07-JUN-12

Monthly Report : 4 / 2012

  

   

Total/Pending/Completed Milestone - 8 / 0 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1301.5602283.68

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2308.01312.6914.692635.39

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20050/03/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
230.76331.17

Ministry Review Date

LatestLastPhysical Progress (%)Status
21-NOV-06100Completed

Monthly Status

Background Information

All four units (Unit-I, Unit-II, Unit-III & Unit-IV) were synchronized with the Northern Grid in March’ 11, March’11, Jan’12 & Mar’12 and are in commercial operation w.e.f. 1st Apr’11, 26th Oct’11, 13th Feb’12 & 1st Apr’ 12 respectively. The station has generated 86.01 MU’s of electrical energy against a target of 90.18MUs Durining the month.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks