Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : RAMAGUNDAM STPP ST - III(NTPC).

Reported Date : 18-JUL-06

MOU Status :

Monthly Report : 1 / 2005

Cost Overrun (%)-   16.37

Time Overrun (Months)-    -12

Total/Pending/Completed Milestone - 39 / 0 / 39

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1780.9902072.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1104.872.7601177.56

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20050/08/2004

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
347.910

Ministry Review Date

LatestLastPhysical Progress (%)Status
21-JUL-040Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone