Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : RIHAND STPP ST - II(NTPC).

Reported Date : 18-JUL-06

MOU Status :

Monthly Report : 9 / 2005

Cost Overrun (%)-   1.99

Time Overrun (Months)-    -8

Total/Pending/Completed Milestone - 64 / 0 / 64

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3384.7703451.97

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2256.99124.8402381.83

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20060/09/2005

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
351.720

Ministry Review Date

LatestLastPhysical Progress (%)Status
03-AUG-050Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone