Reported Date :
23-MAY-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 232.82
|
Time Overrun (Months)-
187
|
Total/Pending/Completed Milestone -
5
/
0
/
5
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| All the major works of Project have been completed except 40.72m HRT rock plug excavation and 2348 m Concrete Lining.
Total 131m HRT overt lining has been completed during March 2024, which comprise of 96m overt lining from face-4 side and 35m steel liner erection in detour portion of HRT from face-3 side. A critical activity of project i.e. steel liner erection in detour portion of HRT has been completed during the month. Mobilization/erection of Gantries in HRT is in progress for overt lining concrete from Face-3, which is expected to be commenced in April 2024. Efforts are being made to expedite the progress of works.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
Award of contract | 0/0 | 0/0 | Pending | Normal | |
Others | 12/2004 | 0/0 | Pending | Normal | |
| Ongoing Milestone | | Completed Milestone | | |