Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL HYDRO-ELECTRIC POWER CORPORATION.
Project Name : PARBATI HEP (4X200 MW) (NHPC) II.

Reported Date : 23-MAY-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   232.82

Time Overrun (Months)-    187

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3919.59013045

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
12827.694.9012832.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20094/20254/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
17-MAY-07100Completed

Monthly Status

Background Information

All the major works of Project have been completed except 40.72m HRT rock plug excavation and 2348 m Concrete Lining. Total 131m HRT overt lining has been completed during March 2024, which comprise of 96m overt lining from face-4 side and 35m steel liner erection in detour portion of HRT from face-3 side. A critical activity of project i.e. steel liner erection in detour portion of HRT has been completed during the month. Mobilization/erection of Gantries in HRT is in progress for overt lining concrete from Face-3, which is expected to be commenced in April 2024. Efforts are being made to expedite the progress of works.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Award of contract0/00/0PendingNormal
Others12/20040/0PendingNormal

Ongoing Milestone

Completed Milestone