Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : KOLDAM HEP (NTPC).

Reported Date : 11-AUG-15

MOU Status : Project Under MOU for 2015-2016

Monthly Report : 6 / 2015

Cost Overrun (%)-   59.48

Time Overrun (Months)-    74

Total/Pending/Completed Milestone - 11 / 1 / 10

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4527.1572207220

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
65447806622

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20090/06/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4810

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-MAY-06100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone