Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL HYDRO-ELECTRIC POWER CORPORATION.
Project Name : SEWA- II H.E.P (NHPC).

Reported Date : 02-FEB-11

Monthly Report : 11 / 2010

  

   

Total/Pending/Completed Milestone - 3 / 0 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
665.460665.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
946.9635.80982.76

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20070/07/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
17-MAY-07100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks