Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL HYDRO-ELECTRIC POWER CORPORATION.
Project Name : TEESTA LOW DAM STAGE III HYDROELECTRIC POWER PROJECT (NHPC).

Reported Date : 05-SEP-13

MOU Status :

Monthly Report : 7 / 2013

Cost Overrun (%)-   111.73

Time Overrun (Months)-    74

Total/Pending/Completed Milestone - 25 / 0 / 25

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
768.9201628

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1467.53001467.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20079/20125/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
99.37140

Ministry Review Date

LatestLastPhysical Progress (%)Status
17-MAY-07100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone