Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : FG UNCHAHAR TPP STAGE-III (1X210MW)(NTPC).

Reported Date : 09-JAN-07

MOU Status :

Monthly Report : 9 / 2006

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 26 / 0 / 26

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
939.280939.28

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
532.23150.350682.58

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20060/09/2006

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
221.490

Ministry Review Date

LatestLastPhysical Progress (%)Status
16-MAY-060Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone