Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : SIPAT STPP STAGE - I (NTPC).

Reported Date : 05-OCT-12

Monthly Report : 8 / 2012

  

   

Total/Pending/Completed Milestone - 60 / 0 / 60

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
8323.3908323.39

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
81943608230

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/200912/20116/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5470

Ministry Review Date

LatestLastPhysical Progress (%)Status
16-MAY-06100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks