Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : KAHAL GAON STPP STAGE - II (NTPC).

Reported Date : 09-NOV-09

Monthly Report : 7 / 2009

  

   

Total/Pending/Completed Milestone - 57 / 0 / 57

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5868.3105868.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4495.6636619.514881.17

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20070/07/2009

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
16-MAY-060Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks