Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NORTH EAST ELECTRIC POWER CORPORATION.
Project Name : KAMENG HYDROELECTRIC PROJECT (NEEPCO).

Reported Date : 09-JUL-21

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 6 / 2021

Cost Overrun (%)-   217.49

Time Overrun (Months)-    134

Total/Pending/Completed Milestone - 30 / 0 / 30

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2496.97927.347927.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
8225.882.433.258231.56

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20092/20212/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
119.340

Ministry Review Date

LatestLastPhysical Progress (%)Status
08-JUN-06100Completed

Monthly Status

Background Information

All the 4 (four) Units of 4 X 150 MW Kameng HEP have been declared for Commercial Operation (COD). The dates of COD of the Units are as follows: Unit – I: 17.06.2020 Unit – II: 01.07.2020 Unit – III: 22.01.2021 Unit – IV: 12.02.2021

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <