Sector Name : POWER.
Agency Name : NATIONAL THERMAL POWER CORPORATION.
Project Name : BARH STPP(3X660MW) NTPC.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   145.16

Time Overrun (Months)-    161

Total/Pending/Completed Milestone - 50 / 1 / 49

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
8692.9721312.1121312.11

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
22199.1690.98022290.14

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20117/20233/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
470.950

Ministry Review Date

LatestLastPhysical Progress (%)Status
13-DEC-2416-MAY-0695Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone