Reported Date :
14-OCT-16
|
MOU Status :
Project Under MOU for 2015-2016
|
Monthly Report :
8
/
2016
|
Cost Overrun (%)- 106.63
|
Time Overrun (Months)-
84
|
Total/Pending/Completed Milestone -
4
/
0
/
4
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Unit-1: Commissioned on 14.02.2016 and COD on 11.03.2016.
Unit-2: Commissioned on 16.03.2016 and COD on 31.03.2016
Unit-3: Commissioned on 03.07.2016 and COD on 17.07.2016.
Unit-4: Commissioned on 11.08.2016 and COD on 19.08.2016.
Project commissioned in August 2016.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |