Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL HYDRO-ELECTRIC POWER CORPORATION.
Project Name : TEESTA LOW DAM HEP, STAGE-IV (4X40 MW) (NHPC).

Reported Date : 14-OCT-16

MOU Status : Project Under MOU for 2015-2016

Monthly Report : 8 / 2016

Cost Overrun (%)-   106.63

Time Overrun (Months)-    84

Total/Pending/Completed Milestone - 4 / 0 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1061.3802193.08

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2013.8425.768.822048.42

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20090/09/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
147.280

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

Unit-1: Commissioned on 14.02.2016 and COD on 11.03.2016. Unit-2: Commissioned on 16.03.2016 and COD on 31.03.2016 Unit-3: Commissioned on 03.07.2016 and COD on 17.07.2016. Unit-4: Commissioned on 11.08.2016 and COD on 19.08.2016. Project commissioned in August 2016.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone