Reported Date :
07-DEC-15
|
MOU Status :
Not Under MOU for 2015-2016
|
Monthly Report :
10
/
2015
|
Cost Overrun (%)- 71.21
|
Time Overrun (Months)-
94
|
Total/Pending/Completed Milestone -
7
/
0
/
7
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
23-SEP-14 | 18-JUL-07 | 100 | Completed |
Monthly Status
|
Background Information
|
|
400KV D/C Mysore - Kozhikode line completed.
400/220KV Kozhikode sub station completed.
Project completed & commissioned in October 2015. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |