Project Summary
Project Summary
Sector Name : POWER.
Agency Name : NATIONAL HYDRO-ELECTRIC POWER CORPORATION.
Project Name : PARBATI H.E.P. STAGE -III (NHPC).

Reported Date : 15-JUL-14

MOU Status :

Monthly Report : 5 / 2014

Cost Overrun (%)-   17.85

Time Overrun (Months)-    46

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2304.5602716

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2349.46002349.46

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20100/08/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
180223.51

Ministry Review Date

LatestLastPhysical Progress (%)Status
17-MAY-070Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone