Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH CENTRAL RAILWAY.
Project Name : GUNA-ETAWAH VIA SHIVPURI-GWALIOR -BHIND NL, (NCR).

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
158.770685

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
681.94.40682.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/19940/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
11

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Construction of RUBs in lieu of LCs has been completed and commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land0/00/0OverNormalProject commissioned.
Delay in supply of indigenous equipments0/00/0OverNormalProject commissioned.
Others0/00/0OverNormalProject commissioned.