Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : DAITARI-KEONJHAR-BANSPANI NEW LINE(ECOR).

Reported Date : 19-OCT-07

Monthly Report : 8 / 2007

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
242.50910

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0837.295.71843

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/19970/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land3/20010/0PendingNormal
Others3/20010/0PendingNormal